Monday, September 29, 2008

Pullin' Romex 12-2

I misunderstood Howell King and ended up being 1/2 hour late this afternoon to begin pulling wires. Howell was his gracious self, however, and we got started drilling holes, nailing on the last few boxes and pulling wires (romex 12-2). We made some real headway and Howell left me with specific instructions for Tuesday & Wednesday when he can't be here to help (he'll be back Thursday afternoon if nothing comes up for him). This is not a very exciting picture but here's the 1000' of romex 12-2 wire on our makeshift "reel":
Here's a picture of one of the the master bedroom receptacles that we got wires pulled to today. Tomorrow I'll continue pulling wires anticipating Howell's return on Thursday for the next step in the process. The hope is that we'll have a rough-in inspection a week from tomorrow and I can start putting the tin ceiling in so the cellulose guy can do his thing with the attic insulation (and south wall).