The tin was still too wet to get up on the roof and finish the flashing and ridge cap so Kim (Campbell) and I began framing the interior walls (hopefully tomorrow we'll finish those two critical things). Additionally, we got the fascia up on the south side of the house (2" X 6"s nailed to the end of the trusses).
Here is a picture of the framing in the master bedroom (13' X 19')... entry to the master bath is on the right but the door is not framed yet (tomorrow):This is the kitchen with a little more framing left to be done (see pressure treated plate on the floor):
This is a view of the office from the living room... the hallway to the master bedroom is on the left (like in the kitchen there is 5 or so more feet of wall that has to be framed... see pressure treated plate on floor):And... this is the rear fascia with the soffit yet to be finished: