Tuesday, September 30, 2008

I pulled wires today...

Here are a couple of pictures of today's taffy pulling at St. Peter's... errr... wire pulling at Brigid's Wood (some will remember that joke?). Tomorrow I'll "neaten up and tighten up" today's work and staple the romex to comply with "the building code" and where ever else it's needed.
This picture will give you some idea of the number of circuits in our house (the tabs are labels for each circuit so Howell King, my electrician, will know what wire goes where... for example: "utility room east wall outlets"). Howell will do his "electrician thing" on Thursday and hook up our electrical panel for the rough-in wiring inspection next week.

Monday, September 29, 2008

Pullin' Romex 12-2

I misunderstood Howell King and ended up being 1/2 hour late this afternoon to begin pulling wires. Howell was his gracious self, however, and we got started drilling holes, nailing on the last few boxes and pulling wires (romex 12-2). We made some real headway and Howell left me with specific instructions for Tuesday & Wednesday when he can't be here to help (he'll be back Thursday afternoon if nothing comes up for him). This is not a very exciting picture but here's the 1000' of romex 12-2 wire on our makeshift "reel":
Here's a picture of one of the the master bedroom receptacles that we got wires pulled to today. Tomorrow I'll continue pulling wires anticipating Howell's return on Thursday for the next step in the process. The hope is that we'll have a rough-in inspection a week from tomorrow and I can start putting the tin ceiling in so the cellulose guy can do his thing with the attic insulation (and south wall).

Sunday, September 28, 2008

Today was all about screwing...

Alexis and I didn't work very long this afternoon. I did get almost all of the HardiPlanks that Kim Campbell and I nailed up on Friday secured with additional screws. The HardiPlank is made out of concrete but it doesn't work like you'd think concrete planks would work. Short pieces are stiff and seem substantial... long pieces are fragile and will break and crumble if not handled carefully. It's the same with trying to screw the planks up. You have to use a hammer to drive the screw into the plank and then use a screw gun to screw it carefully "home." Too much pressure and the screw head crumbles the plank. I'm told the stuff will last for ever but it sure isn't easy to work with! Screw, screws and more screws (black dots):And here we go seamlessly around the corner with the stucco (sometime in October, we hope?):This afternoon Alexis worked in her garden and helped me clean up the job site... she's always a BIG help!

Friday, September 26, 2008

Wood stove flue's in...

Today Kim and I got the wood stove flue completely (and safely) installed... I did the under the roof bracing and Kim caulked and screwed down the rubber boot (flashing) up on the roof. After we pass the rough-in electrical inspection next week, I'll install the tin ceiling and we'll be ready for the cellulose to be blown into the attic. With the house insulated top, bottom and all around, we'll (me, Alexis and our three boys) be able to light off the Tempwood wood stove and be ready for anything "Old Man Winter" can throw at us. Mosby is eagerly anticipating the season's first fire.
Kim and I also got almost all the HardiPlanks nailed on the south side of the house. This will allow the stucco guys to stucco the block and HardiPlank seamlessly on all sides and the gable ends. I still have to screw some of the planks down as some of the nails didn't hold properly.
Tomorrow I plan to do some of this "HardiPlank screwing," glue the CPVC water pipes together and get ready for pulling wires on Monday.

Today was Alexis' birthday (26 September)... the 16th anniversary of her 39th birthday... Happy Birthday, my love!

Thursday, September 25, 2008

Plantar Fasciitis strikes again... BIG TIME!

My plantar fasciitis struck again today and I suffered big time for it. I shuffled around all day like an old crippled-up man... oh, wait... I am an old crippled-up old man. Kim Campbell worked with me all day but I was miserable. I cut OSB and HardiPlanks on the ground and he worked on the ladder measuring and nailing. In spite of my pain we got a lot accomplished. Not only did we finish installing the attic vents and nail up the HardiPlanks on both gable ends, we also were able to reinforce the gable end trusses and tie them in to the roof system more securely. This entire wall will be stuccoed next month.Tomorrow Kim and I will complete the installation of the wood stove flue, begin the HardiPlanking of the south side of the house and - hopefully - get some of the soffit up front and back... I cut the HardiPlank for the soffits yesterday so it should go up pretty fast.
Monday, Howell King and I begin pulling wires. As soon as we pass the rough-in electrical inspection, Kim and I will put up the tin ceiling and I'll call the insulation guy to blow cellulose in the attic and the south wall. We're getting there... slowly but surely.

Tuesday, September 23, 2008

Got started on several important projects...

Today I got started on several important projects that will get completed over the next few days and weeks. First, I was able to install the ceiling support bracket/wood frame for our wood stove. This bracket carries the weight of the insulated stove pipe.
Tomorrow Kim Campbell and I will cut a hole in the tin roof and install the insulated pipe, the flashing, the rubber boot & the chimney cap.
Getting the wood stove installed is very important because without it fully operational we risk the prospect of Mosby divorcing us and finding a family that has a wood fire to keep his dog butt warm this winter. Mosby REALLY likes the wood stove and parks himself almost under it on cold nights (when Alexis saved him from starvation almost three years ago, Mosby had been fending for himself in the woods around Wonder Cave for months come rain or come shine... based on his emaciated condition upon his arrival - he looked like a turkey carcass after Thanksgiving dinner, I think it's safe to say that Mosby is the WORLD's WORST hunter... he really likes having a family, a full tummy and a wood stove). Not to worry Mose-Bose... the Tempwood wood stove will be our primary source of heat in our Irish cottage. We'll have propane back-up but solar on sunny days and the Tempwood on chilly nights is our plan. Here's the bracket/frame in the ceiling (this took some head scratching to install it in just the right place):I also was able to get all but two of the switch boxes and outlet boxes nailed to the studs throughout the house preparing for the wire pulling next week. When Howell King comes next Monday, he and I will run the "Romex" 12-2 wire from the main panel in the master closet to each individual (blue) box. This is a shot of the east end of the kitchen looking through the plumbing wall to the utility room and master closet:Although this is a VERY bad picture of the hole (you have to look VERY closely to even see it in the middle of the second row of AAC block!), this is one of the holes I cut in the AAC block for an electrical receptacle. I still have to cut a chase for the conduit for each box but that is no big deal:Tomorrow when Kim Campbell comes back (he always wants me to meet him at the job site at "O" dark-thirty... ugh!), we'll finish up some things on the roof and gable ends. He works my butt off but we typically get a lot done. Two men can accomplish at least three times as much as a man by himself... "you ALWAYS need someone to hold the other end of the board."

Saturday, September 20, 2008

Getting ready to wire the house!

Howell King, my plumber/electrician, came by this afternoon for some "good old boy consultation." I'm happy to report that he put his stamp of approval on my attempt at plumbing... there are just a few small changes so I can glue the pipe together tomorrow... that's the fun part. Alexis and I bought most of the supplies to wire the house yesterday. Howell will be busy next week but the following week he thought he could come by in the afternoon after work (3:00 PM) and we could get the house wired in 4 or 5 days. In the meantime I can get ready for him by nailing electrical boxes on the studs, etc. After we pass the electrical inspection, it will be time to screw up our white tin ceiling and have the cellulose insulation (11" = R-50) blown in. Sometime next week I plan on getting the insulated pipe installed for Mosby's Tempwood wood stove (it's an AMAZING wood stove that will heat our entire house!)... Mosby dearly loves to lie almost under the stove on really cold evenings... with the mega-insulation and the Tempwood we'll be ready for whatever Old Man Winter brings.
Today I framed in the open space above the front door so that it can be stuccoed:I also framed up the wall in the master bedroom closet where the electric panel will go and insulated the corner with foil/foam/foil (approx R-16):
Slowly but surely we're getting there!